AMERISTAR SUBSTATION

AMERISTAR CASINO

20 MVA ELECTRICAL SUBSTATION

ST. CHARLES, MO

 

BUILDING SYSTEMS DIVISION

 

DEDICATED ELECTRICAL SUBSTATION SERVING AMERISTAR CASINO

 

PRIMARY INCOMING WAS A 34 Kv OVERHEAD LINE FROM UTILITY

 

SECONDARY CONSISTED OF TWO 12,470-VOLT CIRCUITS DELIVERED VIA UNDERGROUND DUCTBANKS AND MAHOLES

 

SWITCHYARD SHELTERED AISLE STUBSTATION AND DUCTBANK DESIGNED TO ACCOMMODATE A SECOND TRANSFORMERAND FUTURE 12,470-VOLT CIRCUITS

 

PRIVATELY FINANCED POWER STATION DESIGNED AND CONSTRUCTED TO MEET THE AGGRESSIVE PROJECT SCHEDULE

 

ALL DESIGN DETAILS WERE REVIEWED AND APPROVED BY THE ELECTRICAL UTILITY